On 12 August 2009, 15 pre-selected members of the Association, attended a breakfast at the Margate Country Club, the purpose of which was to request their participation, in the Gamalakhe Community project.

South Coast Regional Chairman Ray Basson; had invited George Enslin to address the meeting to provide project details, as well as background information. Without hesitation, members came forward and pledged everything needed for completion, it was overwhelming, and absolutely fantastic to witness.

Participant and Pledge details:

Master Builders KwaZulu-Natal
R20000.00
Ugu Municipality
R10000.00
Anthony & Basson
Project Management and Labour
Cee-Hoo
Site Management
Blue Gold
3m3 Concrete for foundation
NPC
Concrete for foundation, floorslab & 5m3 river sand
Aries Building Suppliers
60 pockets cement
Vongo Bricks ‘n Block
bricks & all lintols
Kulucrete
1000 Blocks 6”
Port Shepstone Quarries
10m3 Building and plaster sand
Build It (Port Shepstone)
Usb green / brickforce / dpc / rooftiles & window frames.
Builders Trade Depot
Door frames & Maranti doors & locks
KG Glass
Glazing (6xNC2)
Hi Teck Roofing
All roof timber
Belcom
Roof sheeting / tiles
FS Gonzalves
Painting of all structures new and old
Sonny Bushaya Construction
Electrical work

Site work had already begun on 11 August 2009, for follow up articles and progress reports ….. WATCH THIS SPACE..... It’s initiatives like this, that make one proud to be associated with Master Builders KwaZulu-Natal.

Hans Stols
South Coast Regional Manager