Tuesday, December 8, 2009

Greening Alterations 40 Essex Terrace


The site handover meeting pertaining to the greening alterations and additions to our Essex Terrace premises took place on Monday the 30th of November 2009.

Companies awarded the contract:
  • Bruce Clark Associate Architects - appointed as architect
  • Leigh - Hunt Louis Wanless - appointed as Quantity Surveyors
  • ARUP - appointed as engineers
  • LVE Construction - awarded the contract as main contractor
Areas that were discussed and agreed upon included:
  • Contract parameters
  • Insurances
  • Guarantees
  • Contractual matters
  • Access
  • Site Layout
  • Site Establishment and Preliminaries
  • Site Diary:
  • Site Security
  • Site Instructions
  • Information required and queries by contractor
  • List of subcontractors
  • Contractors Program
  • Compliance with OHS act and regulations
  • Consultants
  • Quantity Surveyor
  • Structural Engineer
  • Land surveyor
  • Safety agent
  • Electrical Engineer
  • Mechanical engineer
Association Executive Director Brandon Abdinor stated that one of the key objectives is for the Master Builders KwaZulu-Natal initiative to become recognized as the benchmark project for greening alterations within Southern Africa.

Watch This Space !!!!!!

Ernest Roper
Webmaster
CONSULT YOUR ASSOCIATION.
WE ARE HERE TO HELP YOU !

No comments: